High FAB/RAW Release info
25
2
00
Posted: Feb 07, 2020   
Votes
Tomaz Ranzinger
Tomaz
 112
Replied 

Raw/Fab qty usually comes into QAD resource authorization date with edi message and data are loaded into customer schedule (menu 7.5.1, or/and 7.5.2 --> 7.5.3 is then generated based on that). To get this info out of QAD you have to delete it from customer schedule or disable them from loading them from edi file. But if customer sends those data, you should first check with customer.

00
Replied: Feb 11, 2020
Votes
David Langschied
David
 4
Replied 

There are entries in the Required Ship Schedule Update for RAW/FAB.  What table are these stored in?

 