Using alternate routing for an extended period of time
33
1
00
Posted: Jan 28, 2020   
Votes
Brent Shooltz
Brent
 67
Replied 

Hi Wendy - yes, this should be possible. 

Whether scheduling discrete or repetitive order types, Item Production Line Maintenance has a field [Start], providing the ability to define the effective date for the item run rate, run crews, Routing & BOM codes to be used when MRP creates planned orders, or when a user directly creates the order in the Master Scheduling Workbench or Production Order Maintenance.

With this [Start] field, you can define multiple effective dates to phase in/out different Routings/Boms.

Brent