Can QAD run MRP for Alternate structure with priority?
110
1
00
Posted: Aug 23, 2019   
Votes
Phill Norrey
Phill
 1359
Replied 
QAD will not run MRP as you suggest.  But you can set up a planning BOM to create the % splits for planning purposes.  However, the best way is that as soon as you have the top level requirement you create a W/O with a status of E (Exploded) and make sure you reference the alternate BOMthen the next time QAD runs it will plan based on the Alternate for that WO.  You could get away with just creating the WO at F but by using E you differentiate it fromanother WO using the regular BOM
10
Replied: Aug 23, 2019