Production hours - Any way to decrease them for a temporary calendar window
133
1
00
Posted: Jun 20, 2019   
Votes
Brent Shooltz
Brent
 67
Replied 

Hi Justin,

In 2018 EE, Site Calendar Exception Maintenance provides the capability you are looking for.  Defining at the site level, you can remove / add capacity for all work center & production line calendars and update MSW/PSW.

In older versions, including our SE releases, there was something equivalent.  Work Center Calendar Maintenance? - I believe if you defined an exeception record at the site level, capacity could be removed/added across all work centers and production lines in MSW/PSW.

Brent